Niah Jaya

 


Building Specifications

Specifications - Commercial Shoplots
Building Structure - Reinforced concrete frame
Roof - Metal roofing
External Wall - Brick Wall
Internal Wall - Brick Wall
Ceiling - General emulsion paint to soffit of reinforced concrete slab for Ground Floor
  - First Floor – generally gypsum board on suspend aluminium tees;
  - Toilets – Asbestos – free cement board
Windows - Natural anodized aluminium – framed windows glazed with colour tinted glass
Doors - Natural anodized aluminium roller shutter to shop front and real
  - Fire rated entrance door to upper  floor
  - Timber door to others
Floor Finishes - Generally cement sand screed
  - Non-slip ceramic tiles to toilet
  - Homogenous tiles to five foot way
Wall Finishes - Glazed ceramic wall tiles up 1500 mm high for toilets
Paintwork - Internal walls – Emulsion paint
  - External Walls – Weatherbond paint
Sanitary Installation - Sanitary fittings:
  2 no wash basin
  3 nos WC’s
Electrical Installation - Concealed wiring
  - Standard lighting and socket points
  - Single phase power supply

 

Location


Niah Jaya Click image to view larger

Site Plan

Niah Jaya Click image to view larger
Niah Jaya Click image to view larger
Niah Jaya Click image to view larger

Plan

Click image to view larger

@ Site Clearance

@ Site Clearance

@ September Progress : Ready for foundation work

@October Progress: Piling work and foundation work

@ November Progress: Ground beam in progress (Block A)

@ November Progress: Ground floor column in progress (Block B)

@ November Progress: First floor slab in progress (Block C)

@ November Progress: Pilling work in progress (Block D)

@ November Progress: Ground Floor reinforced concrete ground floor beams &

     columns of the Shophouse Completed (Block B)

@ November Progress: Ground Floor reinforced concrete ground floor beams &

      columns of the Shophouse Completed (Block C)

@ January Progress: Ground Floor reinforced concrete ground floor beams &

      columns of the Shophouse Completed (Block A)

@ January Progress: First Floor reinforced concrete first floor beams &

      columns of the Shophouse Completed (Block C)

@ January Progress: Pilling work completed (Block D)

@ February Progress: First Floor reinforced concrete first floor beams &

     columns of the Shophouse in progress (Block B)

@ March Progress: Pilling works for the Shophouse Completed (Block G)

@ April Progress: Ground Floor reinforced concrete ground floor beams &

     columns of the Shophouse Completed (Block D)

@ April Progress: Pilling works for the Shophouse Completed (Block E)

@ April Progress: Pilling works for the Shophouse Completed (Block F)

@ May Progress: First Floor reinforced concrete first floor beams &

     columns of the Shophouse in progress (Block A)

@ June Progress : First Floor reinforced concrete first floor beams &

     columns of the Shophouse completed (Block A)

@ June Progress : First Floor reinforced concrete first floor beams &

     columns of the Shophouse completed (Block B)

@ August Progress: Ground Floor reinforced concrete ground floor beams & columns

of the Shophouse in progress (Block G)

@ September Progress: Reinforced concrete beam of the roof of the

Shophouse in progress (Block B)

@ October Progress: Ground Floor reinforced concrete ground floor beams & columns

of the Shophouse in progress (Block G)

@ November Progress: Ground Floor reinforced concrete ground floor beams

& columns of the Shophouse Completed (Block G)

@ December Progress: Reinforced concrete beam of the roof of the Shophouse

in progress (Block C)

@ January Progress: First Floor reinforced concrete first floor beams & columns of the Shophouse in progress (Block B)

@ March Progress : Reinforced concrete floor and beam of the shophouse

@ April progress : Plastering

@ July Progress: Brick wall of the Shophouse completed (Block C)

@ July Progress: Brick wall of the Shophouse completed (Block D)

@ September Progress: Roofing of the Shophouse Completed (Block A)

@ September Progress: Roofing of the Shophouse Completed (Block D)

@ October Progress: Roofing of the Shophouse Completed (Block B & Block C)

@ November Progress: First Floor reinforced concrete first floor beams & columns of the Shophouse in progress (Block E & Block F)

@ April Progress: Brick wall of the Shophouse Completed (Block G)

@ June Progress: Roofing of the Shophouse Completed (Block G)

 

@July Progress: Plastering Internal Wall and External Wall of the Shophouse completed (Block A,B,C,D & G)

 

@ July Progress: Second floor reinforced concrete,  second floor slab & columns of the Shophouse in progress (Block F)

@ October Progress: Brickwall of the Shophouse completed (Block F)

@ December Progress: Roofing of the shophouse completed (Block F)

 

@ January 2017 Progress: Plastering internal wall and external wall of the shophouse completed (Block F)